Friday, June 27, 2014

Project Procurement Management - Conduct Procurements

This process obtains the seller responses, selects a seller and awards a contract. It provides alignment of internal and external stakeholder expectations through established agreements .

Let's take a look at the Inputs, Tools and Techniques, and Outputs of this process.



















1) Procurement Management Plan

  • Describes how the procurement processes will be managed from developing procurement documentation through contract closure
2) Procurement Documents
  • Provide an audit trail for contracts and other agreements
3) Source Selection Criteria
  • Information on the supplier's required capabilities, capacity, deliver dates, product cost, life-cycle cost, technical expertise, and the approach to the contract. 
4) Seller Proposals
  • Form the basic information that will be used by an evaluation body to select one or more successful bidders
5) Project Documents
  • Documents that include risk-related contract decisions 
6) Make-or-Buy Decisions
  • Factors that influence these decisions may include:
    • Core capabilities of the organization
    • Value delivered by vendors meeting the need
    • Risks associated with meeting the need in a cost-effective manner
    • Capability internally compared with the vendor community
7) Procurement Statement of Work
  • Provides suppliers with a clearly stated set of goals, requirements, and outcomes from which they can provide a quantifiable response. 
    • Specifications
    • Quantity desired
    • Quality levels
    • Performance data
    • Period of performance
    • Work location
    • Other requirements
8) Organizational Process Assets
  • Items that may influence Conduct Procurements:
    • Listings of prospectives and previously qualified sellers
    • Information on relevant past experience with sellers, both good and bad
    • Prior agreements
9) Bidder Conferences
  • Meetings between the buyer and all prospective seller prior to submittal of a bid or proposal
  • Also known as contractor conferences, vendor conferences, and pre-bid conferences
10) Proposal Evaluation Techniques
  • Formal evaluation review process will be defined by the buyer's procurement policies. 
11) Independent Estimates
  • An organization can prepare its own independent estimate or get an outside professional to do one so that they can compare the differences in cost to the proposals
12) Expert Judgment
  • have the experts review the seller proposals (contracting, legal, finance, accounting, engineering, design, research, development, sales, and manufacturing) 
13) Advertising
  • Advertise to get more potential sellers to increase the pool of proposals
14) Analytical Techniques
  • Helps organizations identify the readiness of a vendor to provide the desired end state, determine the cost expected to support budgeting, and avoid cost overruns due to changes. 
15) Procurement Negotiations 
  • Clarify the structure, requirements, and other terms of the purchases so that mutual agreement can be reached prior to signing the contract. 
  • Items covered
    • Responsibilities
    • Authority to make changes
    • Applicable terms and governing law
    • Technical and business management approaches
    • proprietary rights
    • Contract financing
    • Technical solutions
    • Overall schedule
    • Payments
    • Price
16) Select Sellers
  • Those that have been judged to be in a competitive range based upon the outcome of the proposal or bid evaluation and who have negotiated a draft contract that will become the actual contract when an award is made. 
17) Agreements
  • Includes terms and conditions and may incorporate other items that the buyer specifies regarding what the seller is to perform or provide. 
  • Also known as - an understanding, a contract, a subcontract, purchase order and is legally binding
  • May include:
    • Statement of work or deliverables
    • Schedule baseline
    • performance reporting
    • period of performance
    • roles and responsibilities
    • seller's place of performance
    • pricing
    • payment terms
    • place of delivery
    • inspection and acceptance criteria
    • warranty
    • product support
    • limitation of liability
    • fees and retainer
    • penalties
    • incentives
    • insurance and performance bonds
    • subordinate subcontractor approvals
    • change request handling
    • Termination clause and alternative dispute resolution (ADR) mechanisms 
18) Resource Calendars
  • Identify the dates on which each specific resource or resource group can be active or idle
19) Change Requests
  • Any change requests go through the Perform Integrated Change Control process
20) Project Management Plan updates
  • May include:
    • Cost baselines
    • Scope baselines
    • Schedule baselines
    • Communications management plan
    • Procurement management plan
21) Project Document Updates
  • May include:
    • Requirements documentation
    • Requirements traceability documentation
    • Risk register
    • Stakeholder register
Source: PMBOK 5th ed. 

6 comments:

  1. Undertaking Management Institute or basically PMI is the lawful body, which gives PMP accreditation subsequent to taking the assessment led by the equivalent. ExcelR PMP Certification

    ReplyDelete
  2. Thanks for sharing this information. I really like your blog post very much. You have really shared a informative and interesting blog post .ExcelR pmp certification

    ReplyDelete
  3. Another great information, i like this kind of blog information really very nice and more new skills to develop after reading that post.
    Procurement Management Software
    Purchase Management Software
    e Procurement Management Software
    Procurement Tracking Software

    ReplyDelete
  4. Somebody necessarily help to make severely posts I might state. This is the first time I frequented your website page and to this point? I surprised with the research you made to create this particular post extraordinary.
    Procurement Management Software
    Procurement Management Software India
    e Procurement Management Software
    Procurement Software India

    ReplyDelete
  5. I would like to thank you for the efforts you have made in writing this article. I am hoping the same best work from you in the future as well.

    Data Science Training in Hyderabad

    ReplyDelete